Sprint 2 timeframe: 4 - 15 May. Note that there is one national holiday during the sprint: 14 May.

Team availability

  • Available resources: Brylie (80%), Juuso (40%), Taija (20%).
  • Total number of hours available: 69 h.

Tasks selected to Sprint 2:

Task 11: Create HTML Mockups for consumer dashboard

Task 24: Set up scaffold

Task 23: Set up project repository

Task 25: Research API Umbrella Gatekeeper

Task 6: Brainstorm session about personas

  • Assigned to Taija Bjorklund
  • Involve also Illya (and Vesa?) in the brainstorming, if possible

Task 34: Research API Umbrella web

Task 8: Document personas

Task 32: Authentication

Task 33: User profiles

Task 36: Learn about Mango/Meteor aggregations